Calculation of waste water discharge in an animal slaughter house http://www.waterandwastewater.com/cgi-bin/yabb/YaBB.pl?num=1142244578
Water usage at plants such as this tend to be affected by the attitudes of both the in-house operators and the local veterinary inspectors to water usage and conervation. My experience of typical "normal" unit loads, (european experience), that can be achieved at a well run slaugher facility are set out below:
Cattle: 0.9 m3 /head and 3.5 kg BOD /head. (This includes an allowance for washing of livestock pens, and delivery vehicles, running / recovery of casings and edible fat, normal slaughtering aspects, very good blood collection, but excludes any allowances for cooking of cuts, pressing of paunch or belly grass materials, or for other value added processing).
Pigs: 0.5 m3/head, and 0.6 kg BOD per head. (This also includes an allowance for washing of livestock pens, and delivery vehicles, running / recovery of casings, normal slaughtering aspects, very good blood collection, but excludes any allowances for cooking, curing, or other valued processing).
Sheep: 0.08m3/head and 0.35 kg BOD per head processed.
(This too includes an allowance for washing of livestock pens, and delivery vehicles, running / recovery of casings, normal slaughtering aspects, very good blood collection, but excludes any allowances for cooking or other value added processing).
COPY RIGHTS : TO AVOID COPYRIGHT VIOLATIONS, ALL POSTS ARE SHOWN ALONG WITH SOURCES FROM WHERE ITS TAKEN. PLEASE CONTACT ME IN MY EMAIL SALEEMASRAF@GMAIL.COM , IF YOU ARE THE AUTHOR AND YOUR NAME IS NOT DISPLAYED IN THE ARTICLE.THE UNINTENTIONAL LAPSE ON MY PART WILL BE IMMEDIATELY CORRECTED.
I HAVE SHARED ALL MY PRACTICAL WATER TREATMENT EXPERIENCES WITH SOLVED EXAMPLE HERE SO THAT ANYBODY CAN USE IT.
SEARCH THIS BLOG BELOW FOR ENVO ,COMPACT STP,ETP,STP,FMR,MBBR,SAFF,IRON,ARSENIC,FLUORIDE,FILTER,RO,UASB,BIO GAS,AERATION TANK,SETTLING TANK,DOSING,AMC.
SEARCH THIS BLOG
Monday, April 30, 2012
Calculation of waste water discharge in an animal slaughter house
Labels:
animal slaughter,
effluent treatment,
waste water
Environmental Entrepreneur,Green Biz.NRN Murthy of Infosys says that we Indians are weak in execution.We need to realize the need and practice of gud project management. Form a group of competent Managers,Give them responsibilities and review the project from day One.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment