COPY RIGHTS : TO AVOID COPYRIGHT VIOLATIONS, ALL POSTS ARE SHOWN ALONG WITH SOURCES FROM WHERE ITS TAKEN. PLEASE CONTACT ME IN MY EMAIL SALEEMASRAF@GMAIL.COM , IF YOU ARE THE AUTHOR AND YOUR NAME IS NOT DISPLAYED IN THE ARTICLE.THE UNINTENTIONAL LAPSE ON MY PART WILL BE IMMEDIATELY CORRECTED.

I HAVE SHARED ALL MY PRACTICAL WATER TREATMENT EXPERIENCES WITH SOLVED EXAMPLE HERE SO THAT ANYBODY CAN USE IT.

SEARCH THIS BLOG BELOW FOR ENVO ,COMPACT STP,ETP,STP,FMR,MBBR,SAFF,IRON,ARSENIC,FLUORIDE,FILTER,RO,UASB,BIO GAS,AERATION TANK,SETTLING TANK,DOSING,AMC.

SEARCH THIS BLOG

Friday, April 21, 2006

ENVIRONMENTAL IMPACT ASSESSMENT STUDIES

A . Scope of work :
EIA / EMP report is based on the --------
Study will be conducted within 10 km radius around the proposed site .
Field data collection of different aspects of environment including Air, Water, Land, Flora & fauna , Agriculture & Socio-economic aspects .
Atleast five monitoring station will be choosen for ambient air quality ( SPM , SO, NO ), Noise monitoring , micro- meteorological information ( Temp, humidity, rainfall, wind speed , wind direction and wind rose diagram ) , surface & ground water characteristics , soil quality etc .
DATA GENERATION
Meteorological information like wind direction,wind velocity,temperature,humidity etc will be collected from nearest IMD station .
Existing vegetation scenario viz. flora & fauna found in the study area.
Socio- economic status and land use pattern of the study area.
Ambient air quality monitoring report
Noise monitoring report
Ground water quality report
Surface water quality report
Soil quality report
Contour mapping of the site
Topography of the site from Surveyor of India
Any prominent feature near the area like lake,bird sanctuary,highway etc
Layout details of the industry
Assessment of gaseous , liquid and solids discharge from the proposed industry.
Assessment of likely impact of above discharge on the various components of the environment.
Pollution control measures to be adopted by the proposed industry .
Complete environmmental plan will be adopted before & after establishment for the industry.
B.Presentation of report in concerned Deptt :
Ministry of Environment & forest ,New Delhi
State pollution control board .
C. Project duration :
1. For base line data collection ----- 3 months
2. Report compilation --------------- 1 month
D. The commercial offer :
The charge of rapid EIA/EMP alongwith the data collection and compilation of report will beRs . 3,75,000/=( Rupees three lacs seventy five thousand only ) .
E . Payment terms :
40 % advance alongwith work order
20 % after collection of base line data ( First progress report )
20 % at the time of draft report submitting
15 % at the time of final report submitting
5 % after approval of the report
NOTE : All payments will be released through demand draft and payable at Delhi .
For ENVO PROJECTS

(SALEEM ASRAF SYED IMDAADULLAH)
Director

No comments: